Aug 19, 2020 | Uncategorized
Building A at Chariya Residence has been completed, and 4 of the 6 units have been furnished and handed over to the happy new owners!
Dec 7, 2019 | Uncategorized
Chariya Residence building A brickwork has been completed, and we are currently installing plumbing and electrical works. Great progress and we are on schedule for completion in early...
Oct 19, 2019 | Uncategorized
Building A roof is complete, we are now well underway with brickwork, electrical and plumbing installations, then we will render all interior and exterior walls, then the fun begins! Doors and windows, tiles, kitchens and baths to come shortly! Click Here for more...
Aug 20, 2019 | Uncategorized
August 20, 2019 Construction Updates. A beautiful day at Chariya Residence! Click main photo for more...
May 13, 2019 | Uncategorized
Things are moving along well at Chariya Residence, and sales also. Pouring concrete columns for the terrace and swimming pool, as well as the on-site restaurant and fitness center. Second-floor construction starting now! It’s a great time to reserve your Chariya...